During the construction of a new vessel, we perform the following work package:
-
Development of a complete set of communication, navigation and hydroacoustics equipment in accordance with the requirements of the classification society, the flag and the terms of reference;
-
Supply of equipment in accordance with the configuration agreed with the shipowner;
-
Advising the main designer on the placement of equipment, its electromagnetic compatibility, compliance with the manufacturer's requirements, making the wiring diagram for the supplied equipment;
-
Preliminary placement of equipment blocks in consoles, correction of prepared seats, windows, fasteners, holes after the fact. Dismantling pre-installed blocks;
-
Adaptation of consoles for the installation of equipment units in accordance with the requirements of the manufacturer and registry with layout adjustment of equipment mounting;
-
Technical support for laying equipment cables in accordance with the specifications of the cable magazine;
-
Development of a scheme of cable canals inside the consoles;
-
Development of working design documentation for the installation and fastening of communication equipment, electro-radio navigation and hydroacoustics in separate sections of the navigator's control panel and other places with the production of a grounding scheme. Carrying out the coordination of this documentation with the Class inspector;
-
Development of working design documentation for the installation of antennas on the upper bridge, mainmast and other places;
-
Laying cables inside the console, with the formation of cable canals;
-
Cable marking;
-
Measurements, continuity of the laid cables, checking the correct marking of cables before connecting to the equipment;
-
Final installation of equipment, antennas on the vessel, cutting cables, connection;
-
Manufacture of plastic information plates and their fasteners at the equipment installation sites;
-
Switching on equipment, commissioning, programming, registration of the COSPAS-SARSAT EPIRB, commission testing of equipment;
-
Measurement of grounding resistance of devices and shielding braids of cables with the preparation of tables and their completion;
-
Measurement of insulation resistance of cables, between cores, between cores and the ship's hull with the preparation of tables and their completion;
-
Development program of mooring and sea trials and its coordination with the registry;
-
Carrying out mooring tests of the installed equipment, presentation to the shipowner and the register;
-
Registration of the Report on the inspection of the GMDSS ship equipment in accordance with the form RMRS 6.3.22.2;
-
Carrying out sea trials of the installed equipment, presentation to the shipowner and the registry.
You can see photos of the work done on the newly built vessel MSTR VSESLAV in the section